The Wind Park of power stations “Bogdanci” entering its final phase of construction. At the field are already uploaded and fully completed all 16 windmills and currently runs activities for connecting the wind park to the electricity network MEPSO.
For connecting the wind park power stations Bogdanci to the distribution network this morning from 5 to 7 were without electricity settlements in the municipality of Gevgelija, Valandovo, Dojran and Bogdanci. The work has already been completed and the four municipalities have normal power supply.
Follows a period of testing the performance of the complete technical equipment after which the facility will enter into production.
It is completed the performance of the necessary infrastructure and accessory facilities at the wind park, the road infrastructure is built, connected to transmission lines, control building and 20/110 kilovolt substation. It remains to be realized the paving of the access road and horticultural activities in the area around the windmills.
PVE “Bogdanci” with 16 windmills flung on 29 hectares is expected to deliver at least 100 GW/Hs naturally sustainable energy, which on annual base is enough to supply 60,000 households of citizens. At the same time, they will increase the installed power of AD ELEM 36.8 MW and the share of renewable sources in its production.
The wind park are built-in turbines, produced by Siemens – Denmark, which are among the best in its class. The installed capacity of each is 2.3 MW, the height of the pillar is 84 meters and the diameter of the propeller is 93 meters.
The realization of the project costs 55.5 million euro, out of which 47.9 million is loan from the Government of the Federal Republic of Germany through KfW Bank, while 7.6 million euro are provided by ELEM’s own funds.